PROJECTS

Find some of our projects below

BAHAMAS
“BPL”

Reception, temporary storage, transport and foundation delivery of 7 Wärtsilä engines, weighing 296 tons each.

GUATEMALA
“APM TERMINALS”

Installation of a Liebherr STS container crane at the port of APM Terminals in Guatemala.

“DOMINICAN REPUBLIC”
“GUZMANCITOS”

Reception, storage and transport of 16 VESTAS V136 wind turbines for the Guzmancitos wind park in th DR.

GUATEMALA
“VIENTO BLANCO”

First transport in the world using a blade-lifter in combination with a pulling truck to deliver 7 Vestas V112 WTGs to the vicinity of an active volcano.

SURINAME
“SURGOLD”

Inland transport and foundation delivery of five Wärtsilä gen-sets of 135 tons each and 3 ball mills, weighing 80 tons and a diameter of 7.96m. The route covered 80 kilometers of dirt road straight through the Surinamese jungle.

COSTA RICA
“TILAWIND”

Transport of 7 Vestas V90 wind towers on 110 km of Costa Rican roads.

TORTOLA
“BVIEC”

Transport and foundation delivery of 3 Wärstilä engines, weighing 167 tons each, and 3 ABB generators(55 tons each) from the port of Purcell up to the BVIEC (British Virgin Islands Electricity Company) jobsite using a 14-axle PST/SL (self-propelled) trailer.

GUATEMALA
“Planta San Juan, Cementos Progreso”

Cementos Progreso and Thyssen-Krupp have built the largest cement plant in Central America.

PANAMÁ
“MINERA PANAMÁ”

During the summer of 2013, we were contracted by the “Minera Panamá” (Panama Mining Company) for the load-out, temporary storage and transport of numerous heavy components, weighing up to 220 tons.

HONDURAS
“RECO”

Inland transport and foundation delivery of four 137 ton Wärtsilä gen-sets from port Hybur on the island of Roatán, Honduras, up to the jobsite, 1.1 km further down the road.

GUATEMALA
“SAN ANTONIO”

July, 2018: Partial replacement of a damaged wind turbine at the San Antonio Wind Park in Guatemala.