HONDURAS

ROATAN “RECO”

Inland transport and foundation delivery of four 137 ton Wärtsilä gen-sets from port Hybur on the island of Roatán, Honduras, up to the jobsite, 1.1 km further down the road. All discharge, temporary storage, transport and foundation delivery of these four components was realized within the proposed 3-week timeframe.